Dorado Development Offshore Project Proposal

Closed 29 Oct 2021

Opened 20 Aug 2021

Overview

Project name: Dorado Development    
Submitted by: Santos    
Titles (where relevant): WA-437-P and WA-438-P            
Submission type: Offshore Project Proposal


Draft for public comment - Dorado Development Offshore Project Proposal 


Project description

Santos WA Northwest Pty Ltd (Santos) and its joint venture partner, Carnarvon Petroleum, propose the Dorado Development in the Bedout Sub-basin, located in Commonwealth waters approximately 140 km offshore from Port Hedland, Western Australia. 

The Dorado Development proposal consists of an initial phase of liquids production, and future nearby tiebacks, with gas reinjection to optimise liquids recovery ahead of a future phase of gas export (which is outside the scope of this OPP). The project area extends across petroleum titles WA-437-P and WA-438-P, and Santos is the Operator of both leases.

Dorado will be designed for liquid handling rates of 100 thousand standard barrels per day (KSTB/d) and gas reinjection capacity of 235 million standard cubic feet per day (MMscf/d) over 20 years.

The Dorado Development will consist of: 

  • a 16 slot wellhead platform (WHP) with ten wells initially (production and gas injection); 
  • a floating production, storage and offloading (FPSO) facility; 
  • subsea flowlines and umbilicals between the WHP and the FPSO facility; and 
  • potential future tiebacks. 

This OPP includes potential for future tiebacks (prospects have not yet been appraised) within the Project Area to augment oil production. These tiebacks will connect to the Dorado WHP and FPSO. All planned petroleum activities, including the future tiebacks, will take place within the Project Area defined for the Dorado Development and will include: 

  • site surveys; 
  • drilling
  • vertical seismic profiling; 
  • construction and installation; 
  • commissioning; 
  • operations and facilities maintenance; and 
  • decommissioning (removal of infrastructure and plug and abandonment of wells). 

Dorado is intended to operate for a life of 20 years (inclusive of potential future tiebacks), commencing operations as early as 2025. 

Timing

Phase/activity

Timing*

Indicative Duration

Financial Investment Decision

Mid 2022

 

Wellhead Platform Installation

2023

6 months

Development Drilling

2024

24 months

FPSO Hook-up and Commissioning

2025

3 months

Future tiebacks

Within operating life

60-70 days per well, depending on exploration success

Production

2026

20 years

 

Project area

Propent contact
Name: Sonja Mavrick    
Phone: (08) 6218 7100
Email address: sonja.mavrick@santos.com
Mailing address: GPO Box 5624, Perth, WA, 6831

Providing your comment

The public comment process provides an opportunity for community members to have their say on environmental management aspects of proposed oil and gas projects. To make a submission click on the link below.

If your comments contain sensitive information or if you are unable to use this platform for any reason please refer to our Making public comment on offshore project proposals information paper for alternative options to have your say.

Please be aware that information that is irrelevant to NOPSEMA’s decision making criteria cannot be considered, such as statements of fundamental objection to oil and gas projects, comments that contain personal threats or profanities, SPAM mail, comments made through online social media channels, petitions and comments that pose questions to NOPSEMA and or/the proponent. NOPSEMA takes threats of a personal nature seriously and will consider legal action should the public comment process be misused to make personal threats to any NOPSEMA employee.